university of minnesota
Willey Hall Partial Roof Replacement |
|
Project Overview |
The purpose of this project is to replace a main section of roof system adjacent to Mondale Hall. The work would also include patching various roof sections and an alternate add will be requested to replace the insulation panels at the mechanical room. The scope of work is detailed in SRI Consultants specification dated July 15, 2009 and drawings dated July 16, 2009.
|
Schedule |
| 1 |
|
8/11/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
8/27/2009 |
|
Submittals Due |
| 3 |
|
9/09/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
9/14/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
9/29/2009 |
|
Pre-Award meeting |
| 6 |
|
10/01/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
E.R. Berwald Roofing Co. Inc. |
Estimated Budget: |
|
$165,000 |
Awarded Cost: |
|
$259,229 |
Awarded Duration: |
|
123 Days |
Scope of Work: |
|
Replace a main section of roof |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|