Project Overview
This project consists of updating the existing light fixtures and the lighting control system including all work identified as per drawings dated 05-24-2006, with the following exception: All new fixtures shall be manufactured by the Kirlin Company, no other manufactures are being considered.
Schedule

No
 
End Date
 
Task
1
 
1/08/07
 
Project Announcement
2
 
1/12/07
 
Site Meetings / Tours
3
 
1/17/07
 
Last Day for Questions
4
 
1/24/07
 
Vendors Proposals and Risk Assessments Due
5
 
1/29/07
 
UMN Identifies Potential Best Value
6
 
2/01/07
 
Pre-Award Meeting
7
 
2/02/07
 
Anticipated Date of Award

Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or email the PBSRG contact listed below.
Award Information
Vendor Name:
  Mayer Electric
Estimated Budget:
  $220,000
Awarded Cost:
  $212,990
Awarded Schedule:
  44 days
Scope of Work:
  Auditorium Lighting Replacement

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):
  9.8

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu