Weaver Densford Pharmacy 5th Floor

Project Overview
The scope of this project for suite 5-110 and 5-120 includes the demolition of existing walls, ceiling, floor covering, light fixtures and construction of new walls/doors, install of new ceiling tile/grid/lights, power/voice/data, patch/paint, coordination of customer purchased system furniture, and install of new flooring.

Schedule

No   End Date   Task
1   4/27/2009   Educational Meeting & Site Walk
2   5/12/2009   Submittals Due
3   5/19/2009   UMN Identifies Potential Best Value
4   5/22/2009   Pre Award Kick Off Meeting
5   6/04/2009   Pre-Award meeting
6   6/05/2009   Anticipated Date of Award

Award Information
Vendor Name:
  M.A. Mortenson Construction
Estimated Budget:
  $340,000
Awarded Cost:
  $195,523
Awarded Duration:
  56 days
Scope of Work:
  Demilition of existing walls

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   10

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu