Demolition of existing walls, doors, casework, flooring, ceilings, lighting. Construction to include new walls/partition/doors, patch/painting, ceiling/lighting, flooring, electrical, mechanical modifications, and coordination of customer purchased furniture and workstations. The General Contractor will apply for the construction permit.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
8/26/08 |
|
Educational Meeting & Site Walk
|
2 |
|
9/12/08 |
|
Submittals Due
|
3 |
|
9/23/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
9/25/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
10/13/08 |
|
Pre-Award meeting
|
6 |
|
10/17/08 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Award Construction |
Estimated Budget: |
|
$95,000 |
Awarded Cost: |
|
$90,862 |
Awarded Schedule: |
|
28 days |
Scope of Work: |
|
Demolition of existing walls, doors, casework, flooring, ceilings, lighting |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
|
|
 |