University of Minnesota
West Bank Security & Surveillance
(584-08-0229) |
|
Project Overview |
Purchase and installation of video surveillance equipment. Contractor will be responsible for all materials, equipment, labor, permits, inspections, schedule, and closeout/punchlist. Contractor will restore landscape to original condition.
|
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
3/13/08 |
|
Educational Meeting & Site Walk
|
2 |
|
3/24/08 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
4/2/08 |
|
UMN Identifies Best Value
|
4 |
|
4/7/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
4/18/08 |
|
Pre Award Meeting
|
6 |
|
4/19/08 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
Siemens Building Technologies |
Estimated Budget: |
|
$80,620 |
Awarded Cost: |
|
$75,820 |
Awarded Schedule: |
|
19 days |
Scope of Work: |
|
Purchase and installation of video surveillance equipment |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
No |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|