West Bank Exterior - Rarig & Humphrey Center

Project Overview
The project consists of remodeling the existing loading dock at Rarig Center, Building #209, University of Minnesota, Minneapolis West Bank Campus, Minnesota, and as indicated in the Contract drawings and specifications. The project will require demolition, removal and re-installation of selected exterior construction elements. Construction consists of new concrete platform and ramp, handrails and associated construction.

The project also includes the remodeling of existing stairs and planters at the Hubert H. Humphrey Center, 301 – 19th Avenue South, University of Minnesota, Minneapolis West Bank Campus, Minnesota, and as indicated in the Contract drawings and specifications. This consists of selected exterior demolition and removal and re-installation of selected exterior construction elements. Construction consists of tuck pointing of existing brickwork, new concrete stairs and handrails.
Schedule

No
 
End Date
 
Task
1
 
8/20/07
 
Educational Meeting & Site Walk
2
 
9/13/07
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
9/20/07
 
UMN Identifies Best Value
4
 
9/27/07
 
Pre Award Kick Off Meeting
5
 
11/08/07
 
Pre Award Meeting
6
 
11/15/07
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  M.A. Mortenson
Estimated Budget:
  $195,000
Awarded Cost:
  $206,800
Awarded Schedule:
  74 days

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):
  9.9

If you have any questions please email John Savicky at John.Savicky@asu.edu