University of Minnesota

University of Minnesota
Veterinary Medicine – Reconfigure Suite 325

Project Overview
The primary objective of this project is to renovate a total of 2,730 gross square feet of the existing laboratory on the third floor of the Veterinary Teaching Hospital. Interior renovation will allow the College to reconfigure the laboratory area to respond to new equipment needs and correct deficient HVAC systems.
Schedule

No
 
End Date
 
Task
1
 
5/11/07
  Educational Meeting & Site Walk
2
 
6/05/07
  Submittals Due (Proposal, RA Plan, EEO)
3
 
6/20/07
  UMN Identifies Best Value
4
 
7/04/07
  Pre Award Kick Off Meeting
5
 
7/11/07
  Pre Award Meeting
6
 
7/12/07
  Anticipated Date of Award

Award Information
Vendor Name:
  Cy-Con
Estimated Budget:
  $975,000
Awarded Cost:
  $951,300
Awarded Schedule:
  110 days
Scope of Work:
  Renovate the existing laboratory on the third floor of the Veterinary
Teaching Hospital

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  No
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  9
Final rating of contractor (10 max):   8.9