Vet Science Renovate Lab 3rd Floor

Project Overview
The scope of this project will include demolition, general, mechanical and electrical remodeling to create an approximate 800 GSF wet chemistry laboratory within the existing Vet Science building.
Schedule

No
 
End Date
 
Task
1
 
1/09/08
 
Educational Meeting & Site Walk
2
 
1/24/08
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
2/07/08
 
UMN Identifies Potential Best Value
4
 
2/21/08
 
Pre Award Kick Off Meeting
5
 
2/28/08
 
Pre Award Meeting
6
 
3/03/08
 
Anticipated Date of Award

Award Information
Vendor Name:
  Falls & Nyhusmoen Construction
Estimated Budget:
  $ 330,000
Awarded Cost:
  $ 328,620
Awarded Schedule:
  95 days

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.

If you have any questions please email John Savicky at John.Savicky@asu.edu