Demolition, general, mechanical and electrical remodeling to create an approximate 800 GSF wet chemistry laboratory within the existing Vet Science building.
|
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
5/11/07 |
|
Educational Meeting & Site Walk |
2 |
|
5/25/07 |
|
Submittals Due (Proposal, RA Plan, EEO) |
3 |
|
6/13/07 |
|
UMN Identifies Best Value |
4 |
|
6/26/07 |
|
Pre Award Kick Off Meeting |
5 |
|
7/17/07 |
|
Pre Award Meeting |
6 |
|
7/26/07 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
Falls & Nyhusmoen Construction |
Estimated Budget: |
|
$170,000 |
Awarded Cost: |
|
$318,000 |
Awarded Schedule: |
|
78 days |
Scope of Work: |
|
Remodeling to create a chemistry laboratory within the existing Vet Science |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
|
|
Closeout Status |
Vendor met proposed schedule: |
|
No |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
9.5 |
Final rating of contractor (10 max): |
|
9.8 |
|
|