The scope of this project is to expand the Pharmacy Department to comply with the State Board of Pharmacy. As part of that mandate, Pharmacy must comply with the new 797 regulations. The scope includes the purchase and install of a ducted hood for drug preparation and the install of ducting on a second laminar hood currently in place in room 346. Additional work includes any code upgrades required for this space. The successful architect must have previous experience in design of Pharmacy facilities and experience working with the State Board of Pharmacy.

Schedule

No   End Date   Task
1   10/19/09   Educational Meeting & Site Walk
2   10/28/09   Submittals Due (Proposal, RA Plan, EEO)
3   11/05/09   UMN Identifies Potential Best Value
4   11/10/09   Pre Award Kick Off Meeting
5   11/18/09   Pre Award Meeting
6   11/23/09   Anticipated Date of Award

Award Information
Vendor Name:
  Sebesta Blomberg
Estimated Budget:
  $20,000
Awarded Cost:
  $17,700
Awarded Duration:
  60 days