VCRC – 2nd Floor Cardiology

Project Overview
Renovation of the 2nd floor VCRC Cardiology area. Work to include demolition of existing walls, ceilings, utilities and construction of a new office suite, wall and floor finishes, ceiling, lighting, mechanical, power/voice/data to support Cardiology. Contractor to be responsible for coordinating customer provided furniture for system furniture install.

Schedule

No   End Date   Task
1   6/9/2009   Educational Meeting & Site Walk
2   6/24/2009   Submittals Due
3   7/2/2009   UMN Identifies Potential Best Value
4   7/7/2009   Pre Award Kick Off Meeting
6   7/20/2009   Pre Award Meeting
7   7/24/2009   Anticipated Date of Award

Award Information
Vendor Name:
  Reiling Construction
Estimated Budget:
  $200,000
Awarded Cost:
  $190,438
Awarded Duration:
  61 days
Scope of Work:
  Renovation of 2nd Floor Cardiollgy Area

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.7

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu