University of Minnesota
VCRC – 2nd Floor Cardiology |
|
Project Overview |
Renovation of the 2nd floor VCRC Cardiology area. Work to include demolition of existing walls, ceilings, utilities and construction of a new office suite, wall and floor finishes, ceiling, lighting, mechanical, power/voice/data to support Cardiology. Contractor to be responsible for coordinating customer provided furniture for system furniture install.
|
Schedule |
| 1 |
|
6/9/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
6/24/2009 |
|
Submittals Due |
| 3 |
|
7/2/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
7/7/2009 |
|
Pre Award Kick Off Meeting |
| 6 |
|
7/20/2009 |
|
Pre Award Meeting |
| 7 |
|
7/24/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Reiling Construction |
Estimated Budget: |
|
$200,000 |
Awarded Cost: |
|
$190,438 |
Awarded Duration: |
|
61 days |
Scope of Work: |
|
Renovation of 2nd Floor Cardiollgy Area |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
9.7 |
|
|