UOP Suite 117 Remodel of OIT Offices

Project Overview
This project consists of the remodeling of the OIT offices at the university office plaza
Schedule

No
 
End Date
 
Task
1
 
7/24/07
 
Educational Meeting & Site Walk
2
 
7/31/07
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
8/01/07
 
UMN Identifies Best Value
4
 
8/02/07
 
Pre Award Kick Off Meeting
5
 
8/08/07
 
Pre Award Meeting
6
 
8/09/07
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  LS Black Constructors
Estimated Budget:
  $38,000
Awarded Cost:
  $49,400
Awarded Schedule:
  28 days
Scope of Work:
  Remodeling of the OIT offices at the University Office Plaza
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):
  9.5