UOP Suite 111 Remodel of Tax Offices |
|
Project Overview |
This project consists of remodeling of tax offices at the university office plaza
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
7/24/07 |
|
Educational Meeting & Site Walk
|
2 |
|
7/31/07 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
8/01/07 |
|
UMN Identifies Best Value
|
4 |
|
8/02/07 |
|
Pre Award Kick Off Meeting |
5 |
|
8/08/07 |
|
Pre Award Meeting
|
6 |
|
8/09/07 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
LS Black Constructors, Inc. |
Estimated Budget: |
|
$31,000 |
Awarded Cost: |
|
$49,250 |
Awarded Schedule: |
|
31 days |
Scope of Work: |
|
This project consists of remodeling of tax offices at the university office plaza |
|
|
Closeout Status |
Vendor met proposed schedule: |
|
No |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
Final rating of contractor (10 max): |
|
8.5 |
|
|