University of Minnesota
University Office Plaza – Suite 130 / 140 |
|
Project Overview |
The scope of work is based on the drawing intent, and includes but not limited to:
Demolition: Carpet, walls, ceilings, electrical, video equipment, marker board, mail slot, etc.
Architectural: Walls, ceilings, doors, carpet, casework, finishes
Mechanical: Modify existing fire protection as required to match new room layout
Electrical: Lighting, power, voice/data, projection equipment provisions, etc.
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
2/20/08 |
|
Educational Meeting & Site Walk
|
2 |
|
3/05/08 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
3/11/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
3/14/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
3/28/08 |
|
Pre Award Meeting |
6 |
|
3/31/08 |
|
Anticipated Date of Award
|
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or email the PBSRG contact listed below. |
|
Award Information |
Vendor Name: |
|
James Steele Construction Company |
Estimated Budget: |
|
$ 60,000 |
Awarded Cost: |
|
$69,218 |
Awarded Schedule: |
|
28 days |
Scope of Work: |
|
Based on drawing intent with demolition, architectural, mechanical and
electrical work |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|
|
|
 |