University of Minnesota
Transportation and Safety Building – Phase II |
|
Project Overview |
The Center for Transportation Studies desires to create more flexible office spaces and add new demountable wall offices to the existing office area which is planned to be partially vacated.
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
9/06/07 |
|
Educational Meeting & Site Walk
|
2 |
|
9/20/07 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
10/04/07 |
|
UMN Identifies Best Value
|
4 |
|
10/10/07 |
|
Pre Award Kick Off Meeting |
5 |
|
10/24/07 |
|
Pre Award Meeting
|
6 |
|
10/25/07 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
Tarraf Construction |
Estimated Budget: |
|
$125,000 |
Awarded Cost: |
|
$163,430 |
Awarded Schedule: |
|
66 days |
Scope of Work: |
|
Create more flexible office spaces and add new demountable wall offices |
|
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
Final rating of contractor (10 max): |
|
9.9 |
|
|