Transportation and Safety Building – Phase II

Project Overview
The Center for Transportation Studies desires to create more flexible office spaces and add new demountable wall offices to the existing office area which is planned to be partially vacated.
Schedule

No
 
End Date
 
Task
1
 
9/06/07
 
Educational Meeting & Site Walk
2
 
9/20/07
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
10/04/07
 
UMN Identifies Best Value
4
 
10/10/07
 
Pre Award Kick Off Meeting
5
 
10/24/07
 
Pre Award Meeting
6
 
10/25/07
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Tarraf Construction
Estimated Budget:
  $125,000
Awarded Cost:
  $163,430
Awarded Schedule:
  66 days
Scope of Work:
  Create more flexible office spaces and add new demountable wall offices
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):
  9.9