Tate Physics Chilled Water

Project Overview
The University of Minnesota (UMN) implemented the PIPS process to select a vendor to remove existing chiller waterlines and controls and replace with new chiller waterlines including electrical and all related construction as required.
Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Metropolitan Mechanical Contractors, Inc.
Estimated Budget:
  $490,000
Awarded Cost:
  $465,700
Awarded Schedule:
  75 days
Scope of Work:
  Renovate chiller waterlines

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.63