Project Overview |
Dig and install a pit in Tate Lab of Physics Building that will be used to host a dilution refrigerator which has an outer hollow dewar and an inner insert. The insert is usually pulled upwards from the dewar, or the dewar is dropped downwards while keeping the insert fixed.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
9/16/08 |
|
Educational Meeting & Site Walk
|
2 |
|
9/30/08 |
|
Submittals Due
|
3 |
|
10/6/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
10/8/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
10/22/08 |
|
Pre-Award meeting
|
6 |
|
10/27/08 |
|
Anticipated Date of Award |
|
|