university of minnesota
St. Paul Campus Exterior Card Reader |
|
Project Overview |
Installation of Card Access and door monitoring system in Borlaug Hall and Soils and Science.
Installation of Card Access System.
Contractor will be responsible for all materials, Patching & Painting, equipment, hardware, labor, garbage removal, housekeeping, permits, inspections, schedule, and closeout / punch list unless otherwise noted. Contractor will be expected to coordinate all work involving Networking & Telecommunications Services (NTS) and Department of Central Security (DCS). Contractor will be responsible to coordinate their work schedule with building occupants. Parking and security during the project is the responsibility of the Contactor. Any work preformed in hazardous areas must be done by trained, certified personnel.
|
Schedule |
| 1 |
|
4/02/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
4/29/2009 |
|
Submittals Due |
| 3 |
|
5/04/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
5/12/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
5/20/2009 |
|
Pre-Award meeting |
| 6 |
|
5/27/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Siemens Building Technologies |
Estimated Budget: |
|
$70,000 |
Awarded Cost: |
|
$64,930 |
Awarded Duration: |
|
23 days |
Scope of Work: |
|
Card Reader Installation |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|
|
|
 |