Shepherd Labs - Remodel Labs 340, 344, and 350 |
|
Project Overview |
The Shepherd Lab Remodel rooms 340, 344, 350 are included in the base scope of the project. We will also have a separate price break out for room 356 as well. Includes Demolition of CMU dividing wall, construction of office and dark room, two new fume hoods, HVAC, Electrical, Plumbing, Lab countertops/cabinets and misc. construction tasks.
This project will take place at Shepherd Labs, located at 100 Union Street SE, Minneapolis, MN 55455.
|
Schedule |
| 1 |
|
4/06/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
4/20/2009 |
|
Submittals Due |
| 3 |
|
4/28/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
5/05/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
5/19/2009 |
|
Pre-Award meeting |
| 6 |
|
5/22/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
AECIX, Inc. |
Estimated Budget: |
|
$28,131.00 |
Awarded Cost: |
|
$23,329.00 |
Awarded Duration: |
|
45 Days |
Scope of Work: |
|
Remodel of Shepard Rooms 340, 344, 350 |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
|
|
 |