SE Steam Plant Break & Locker Room Remodel |
|
Project Overview |
This is two small projects that are combined and phased to be implemented one after the other to allow the first phase to be completed and put into use before the second phase demolition is begun. The scope of work for remodeling of space in the historic Southeast Steam Plant west on the Minneapolis Campus on the north bank of the river at 600 Main Street SE includes toilets, showers, locker rooms and a conference / lunch room.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
8/25/08 |
|
Educational Meeting & Site Walk
|
2 |
|
9/4/08 |
|
Submittals Due
|
3 |
|
9/18/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
9/22/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
10/9/08 |
|
Pre-Award meeting
|
6 |
|
10/13/08 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
KM Building Co |
Estimated Budget: |
|
$368,000 |
Awarded Cost: |
|
$241,575 |
Awarded Schedule: |
|
32 days |
Scope of Work: |
|
Remodeling of space |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|