PWB - Lab Remodel – Center for Drug Design

Project Overview
The scope of this project includes removal of lab case work, relocation of existing fume hood, construction of a new wall separating the existing lab, install of additional new case work, plumbing, electrical, and HVAC modifications.
Schedule

No
 
End Date
 
Task
1
 
2/29/08
 
Educational Meeting & Site Walk
2
 
3/14/08
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
3/20/08
 
UMN Identifies Best Value
4
 
3/28/08
 
Pre Award Kick Off Meeting
5
 
4/11/08
 
Pre Award Meeting
6
 
4/15/08
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  M.A. Mortenson Company
Estimated Budget:
  $500,000
Awarded Cost:
  $403,289
Awarded Schedule:
  71 days
Scope of Work:
  Removal of lab Case Work, relocation of existing fumehood

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.

If you have any questions please email John Savicky at John.Savicky@asu.edu