PWB Remodel Suite 6-240 |
|
Project Overview |
The work consists of the renovation and remodel of the existing office of the Dept of Family Medicine and Community Health, Emergency Medicine and Ophthalmology.
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
5/29/08 |
|
Educational Meeting & Site Walk
|
2 |
|
6/12/08 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
6/23/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
6/26/08 |
|
Pre Award Kick Off Meeting |
5 |
|
7/8/08 |
|
Pre Award Meeting
|
6 |
|
7/11/08 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Graham Penn-Co Construction Inc. |
Estimated Budget: |
|
$75,000 |
Awarded Cost: |
|
$127,338 |
Awarded Schedule: |
|
82 days |
Scope of Work: |
|
Renovation and remodel of the existing office |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|