University of Minnesota
PWB Room 7-158B Upgrade |
|
Project Overview |
The scope of this project includes upgrading the existing walls, door, and dampers for room 7-158B to meet the 2 hour fire rating requirements.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
11/04/08 |
|
Educational Meeting & Site Walk
|
2 |
|
11/21/08 |
|
Submittals Due
|
3 |
|
11/28/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
12/03/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
12/12/08 |
|
Pre-Award meeting
|
6 |
|
12/18/08 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
M.A. Mortenson Company |
Estimated Budget: |
|
$45,000 |
Awarded Cost: |
|
$46,504 |
Awarded Schedule: |
|
30 days |
Scope of Work: |
|
Upgrading the existing walls, door, and dampers |
|
|