University of Minnesota
PWB – Replace Cooling Units-Room B-295 |
|
Project Overview |
Intent Is to replace three existing operational Liebert III cooling units with two new air conditioning cooling units. This includes adding an additional riser for increased reliability. Work is to be completed in a secured area, without interruption to equipment operation inside room B-295. The contractor is responsible for application and payment of all building permits.
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
7/15/2008 |
|
Educational Meeting & Site Walk
|
2 |
|
7/29/2008 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
8/5/2008 |
|
UMN Identifies Potential Best Value
|
4 |
|
8/7/2008 |
|
Pre Award Kick Off Meeting
|
5 |
|
8/21/2008 |
|
Pre-Award Meeting
|
6 |
|
8/26/2008 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Egan Company |
Estimated Budget: |
|
$ 477,000 |
Awarded Cost: |
|
$ 461,710 |
Awarded Schedule: |
|
73 days |
Scope of Work: |
|
Replace three existing operational cooling units |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|