Peik Hall – City Water Connection

Project Overview
Intent is to remove and replace existing water service to Peik Hall and Peik Gymnasium with a new direct water service connection to each building, from the city water main.
Schedule

No
 
End Date
 
Task
1
 
6/24/2008
 
Educational Meeting & Site Walk
2
 
7/11/2008
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
7/18/2008
 
UMN Identifies Potential Best Value
4
 
7/23/2008
 
Pre Award Kick Off Meeting
5
 
8/6/2008
 
Pre-Award Meeting
6
 
8/11/2008
 
Anticipated Date of Award

Award Information
Vendor Name:
  Metropolitan Mechanical Contractors
Estimated Budget:
  $ 116,000
Awarded Cost:
  $ 139,000
Awarded Schedule:
  49 days
Scope of Work:
  Remove & Replace existing water service

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.

If you have any questions please email John Savicky at John.Savicky@asu.edu