Peik Hall – City Water Connection |
|
Project Overview |
Intent is to remove and replace existing water service to Peik Hall and Peik Gymnasium with a new direct water service connection to each building, from the city water main.
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
6/24/2008 |
|
Educational Meeting & Site Walk
|
2 |
|
7/11/2008 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
7/18/2008 |
|
UMN Identifies Potential Best Value
|
4 |
|
7/23/2008 |
|
Pre Award Kick Off Meeting
|
5 |
|
8/6/2008 |
|
Pre-Award Meeting
|
6 |
|
8/11/2008 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Metropolitan Mechanical Contractors |
Estimated Budget: |
|
$ 116,000 |
Awarded Cost: |
|
$ 139,000 |
Awarded Schedule: |
|
49 days |
Scope of Work: |
|
Remove & Replace existing water service |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|