Installation of Video Surveillance and Card Access System. Contractor will be responsible for all materials, equipment, hardware, labor, garbage removal, housekeeping, permits, inspections, schedule, and closeout / punch-list unless otherwise noted. Contractor will be expected to coordinate all work involving Networking & Telecommunications Services (NTS) and Department of Central Security (DCS). Contractor will be responsible to coordinate their work schedule with building occupants. Parking and security during the project is the responsibility of the Contactor. Any work preformed in hazardous areas must be done by trained, certified personnel.

Schedule

No   End Date   Task
1   12/29/10   Educational Meeting & Site Walk
2   01/22/10   Submittals Due (Proposal, RA Plan, EEO)
3   02/05/10   Interviews
4   02/09/10   UMN Identifies Potential Best Value
5   02/12/10   Pre Award Kick Off Meeting
6   02/26/10   Pre Award Meeting
7   03/02/10   Anticipated Date of Award

Award Information
Vendor Name:
  Siemens Building Technologies
Estimated Budget:
  $445,000
Awarded Cost:
  $585,210
Awarded Duration:
  102 days
Scope of Work:
  Installation of Video Surveillance & Card Access System

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu
Contact Us