Hasselmo Hall Nanoliter Crystallization

Project Overview
Demolition of existing walls, doors, casework, flooring, ceilings, lighting. Construction to include new walls/partition/doors, patch/painting, ceiling/lighting, flooring, electrical, mechanical modifications, and coordination of customer purchased furniture and workstations. The General Contractor will apply for the construction permit.

Schedule

No   End Date   Task
1   11/02/09   Educational Meeting & Site Walk
2   11/17/09   Submittals Due (Proposal, RA Plan, EEO)
3   11/24/09   UMN Identifies Potential Best Value
4   11/30/09   Pre Award Kick Off Meeting
5   12/09/09   Pre Award Meeting
6   12/14/09   Anticipated Date of Award

Award Information
Vendor Name:
  Sheehy Construction
Estimated Budget:
  $ $165,000
Awarded Cost:
  $119,700
Awarded Duration:
  59 days
Scope of Work:
  Remodel rooms to accommodate new equipment

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu