Project Overview
Install new pipe on existing steam lines and steam valves in deep tunnels, for a tunnel distance of 1,100 feet. This includes two 14’ steam pipes and one 3” steam pipe. Install additional steam traps in existing pipe. Install pipe support between pipe station and pipe.

Schedule

No   End Date   Task
1   8/10/2009   Educational Meeting & Site Walk
2   8/14/2009   Submittals Due (Proposal, RA Plan, EEO)
3   8/19/2009   UMN Identifies Potential Best Value
4   8/20/2009   Pre Award Kick Off Meeting
5   8/27/2009   Pre Award Meeting
6   8/28/2009   Anticipated Date of Award

Award Information
Vendor Name:
  Northern Air Corporation
Estimated Budget:
  $400,000
Awarded Cost:
  $497,195
Awarded Duration:
  52 days
Scope of Work:
  Install new pipe insulation on existing steam lines

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.8

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu