Mpls Utility Tunnel - Pipe Insulation |
|
Project Overview |
Install new pipe on existing steam lines and steam valves in deep tunnels, for a tunnel distance of 1,100 feet. This includes two 14’ steam pipes and one 3” steam pipe. Install additional steam traps in existing pipe. Install pipe support between pipe station and pipe.
|
Schedule |
| 1 |
|
8/10/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
8/14/2009 |
|
Submittals Due (Proposal, RA Plan, EEO) |
| 3 |
|
8/19/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
8/20/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
8/27/2009 |
|
Pre Award Meeting |
| 6 |
|
8/28/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Northern Air Corporation |
Estimated Budget: |
|
$400,000 |
Awarded Cost: |
|
$497,195 |
Awarded Duration: |
|
52 days |
Scope of Work: |
|
Install new pipe insulation on existing steam lines |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
9.8 |
|
|