Project Overview
Replacement of 3 domestic water booster pumps, including all modifications as noted in the Engineered Scope Document dated October 9, 2008.

Schedule

No
 
End Date
 
Task
1
 
10/23/08
 
Educational Meeting & Site Walk
2
 
11/06/08
 
Submittals Due
3
 
11/13/08
 
UMN Identifies Potential Best Value
4
 
11/19/08
 
Pre Award Kick Off Meeting
5
 
12/04/08
 
Pre-Award meeting
6
 
12/08/08
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Metropolitan Mechanical Contractors
Estimated Budget:
  $165,000
Awarded Cost:
  $136,900
Awarded Schedule:
  53 days
Scope of Work:
  Replace 3 domestic water booster pumps

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.

If you have any questions please email John Savicky at John.Savicky@asu.edu
Contact Us