Moos MCB Plaza Water Infiltration |
|
Project Overview |
The project consists of repairing of the waterproofing system within the vicinity of the plaza drain above Auditorium 2-530 at the University of Minnesota, Moos Plaza and replacement of the plaza surface layers as noted in the contract documents.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
11/10/08 |
|
Educational Meeting & Site Walk
|
2 |
|
11/26/08 |
|
Submittals Due
|
3 |
|
12/05/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
12/09/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
12/22/08 |
|
Pre-Award meeting
|
6 |
|
12/23/08 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Sheehy Construction |
Estimated Budget: |
|
$103,000 |
Awarded Cost: |
|
$42,300 |
Awarded Schedule: |
|
53 days |
Scope of Work: |
|
Repair of the waterproofing system |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|