University of Minnesota

University of Minnesota
Mondale Hall

Project Overview
This project consists of updating lighting over the book stacks in the Law Library at Mondale Hall, located at 229 - 19th Avenue South, Minneapolis campus in accordance with the following objectives:
  • Item #1: Install new electrical wiring from existing floor power outlets to book stack lighting fixtures and timer controlled switches.
  • Item #2: Replace existing T12 lamps with energy efficient lamps and ballast. It is our intention to have an increased lighting level over existing conditions. Existing light fixtures are not bright enough.
  • Item #3: Replace existing 3-way light switches and timer control circuits.
Schedule

No
 
End Date
 
Task
1
 
12/05/06
 
Educational Meeting & Site Walk
2
 
12/13/06
 
Submittals Due
3
 
12/18/06
 
UMN Identifies Best Value
4
 
12/18/06
 
Pre-Award Kick Off Meeting
5
 
12/21/06
 
Pre-Award Meeting
6
 
12/27/06
 
Anticipated Date of Award

Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Gephart Electric
Estimated Budget:
  $160,000
Awarded Cost:
  $143,325
Awarded Schedule:
  133 days
Scope of Work:
  Updating lighting over the book stacks

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   10



If you have any questions please email John Savicky at John.Savicky@asu.edu