Middlebrook Hall Fire Pump Controller

Project Overview
Consists of replacing fire pump controller, automatic transfer switch and main disconnect and associated work.
Schedule

No
 
End Date
 
Task
1
 
9/21/06
 
Educational Meeting & Site Walk
2
 
10/05/06
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
10/11/06
 
UMN Identifies Best Value
4
 
10/12/06
 
Pre Award Kick Off Meeting
5
 
10/23/06
 
Pre Award Meeting
6
 
10/24/06
 
Anticipated Date of Award

Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Gephart Electric
Estimated Budget:
  $120,000
Awarded Cost:
  $73,200
Awarded Schedule:
  97 days
Scope of Work:
  Replace fire pump controller & transfer switch

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  No, 120 days (due to winter conditions)
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.63



If you have any questions please email John Savicky at John.Savicky@asu.edu