University of Minnesota

university of minnesota
Mayo Garage - Structural Shoring

Project Overview
The scope of this project is to remove all loose concrete from the upper deck of the Mayo Garage and install structural shoring as recommended in the Walker report on the Mayo Garage dated Mar 18, 2009. This work will be limited to the fenced area for vehicle access to the interior loading dock of the Mayo Garage. The selected contractor will need to consult with Walker Restoration Consultants to ensure compliance with their design.

Schedule

No   End Date   Task
1   5/11/2009   Educational Meeting & Site Walk
2   5/27/2009   Submittals Due
3   6/08/2009   UMN Identifies Potential Best Value
4   6/16/2009   Pre Award Kick Off Meeting
5   6/30/2009   Pre-Award meeting
6   7/06/2009   Anticipated Date of Award

Award Information
Vendor Name:
  M.A. Mortenson Construction
Estimated Budget:
  $190,000
Awarded Cost:
  $78,058
Awarded Duration:
  70 days
Scope of Work:
  To remove all loose concrete from the upper deck

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  No
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   10

If you have any questions please email Anthony Perrenoud at aperreno@exchange.asu.edu
Contact Us