university of minnesota
Mayo Garage - Structural Shoring |
|
Project Overview |
The scope of this project is to remove all loose concrete from the upper deck of the Mayo Garage and install structural shoring as recommended in the Walker report on the Mayo Garage dated Mar 18, 2009. This work will be limited to the fenced area for vehicle access to the interior loading dock of the Mayo Garage. The selected contractor will need to consult with Walker Restoration Consultants to ensure compliance with their design.
|
Schedule |
| 1 |
|
5/11/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
5/27/2009 |
|
Submittals Due |
| 3 |
|
6/08/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
6/16/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
6/30/2009 |
|
Pre-Award meeting |
| 6 |
|
7/06/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
M.A. Mortenson Construction |
Estimated Budget: |
|
$190,000 |
Awarded Cost: |
|
$78,058 |
Awarded Duration: |
|
70 days |
Scope of Work: |
|
To remove all loose concrete from the upper deck |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
No |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|