The scope of this project includes construction services for the cosmetic upgrades to a portion of “B” Corridor in the Mayo Building. Work includes new carpet patch/paint, install of additional electrical/data outlets, minor demolition of interior wall partition, new lighting/ceiling, HVAV, and any required Code upgrades.
|
Schedule |
| 1 |
|
02/17/10 |
|
Educational Meeting & Site Walk |
| 2 |
|
03/01/10 |
|
Submittals Due (Proposal, RA Plan, EEO) |
| 3 |
|
03/08/10 |
|
UMN Identifies Potential Best Value |
| 4 |
|
03/11/10 |
|
Pre Award Kick Off Meeting |
| 5 |
|
03/18/10 |
|
Pre Award Meeting |
| 6 |
|
01/23/10 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
M.A. Mortenson |
Estimated Budget: |
|
$350,000 |
Awarded Cost: |
|
$404,500 |
Awarded Duration: |
|
63 days |
Scope of Work: |
|
Upgrading the 5th floor of the Mayo Building |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
|
|
 |