University of Minnesota
Mayo 5th Floor Urology |
|
Project Overview |
The scope of this project includes design for the cosmetic upgrades to a portion of “B” Corridor in the Mayo Building. Work includes new carpet, patch/paint, install of additional electrical/data outlets, minor demolition of interior wall partition, new lighting/ceiling, and any required Code upgrades.
|
Schedule |
| 1 |
|
09/30/09 |
|
Educational Meeting & Site Walk |
| 2 |
|
10/09/09 |
|
Submittals Due (Proposal, RA Plan, EEO) |
| 3 |
|
10/19/09 |
|
UMN Identifies Potential Best Value |
| 4 |
|
10/22/09 |
|
Pre Award Kick Off Meeting |
| 5 |
|
10/30/09 |
|
Pre Award Meeting |
| 6 |
|
11/04/09 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
C.M. Architecture |
Estimated Budget: |
|
$30,000 |
Awarded Cost: |
|
$18,900 |
Awarded Duration: |
|
42 days |
Scope of Work: |
|
Cosmetic upgrades in Mayo Building |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
|
|
 |