The scope of this project includes removing and replacing the suspended ceiling system and lighting, carpet replacement, minor pluming fixture removal/cap lines, shelving and misc item removal, patching and painting. The contractor will be responsible to obtaining the construction permit. Several of the rooms are currently occupied. The contractor will be responsible for coordinating with the customer for access to these rooms. Asbestos containing materials are present under some of the carpeted areas. The contractor will be responsible for coordinating the asbestos removal. Asbestos removal will be paid for under separate contract.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
10/21/08 |
|
Educational Meeting & Site Walk
|
2 |
|
11/05/08 |
|
Submittals Due
|
3 |
|
11/14/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
12/01/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
12/12/08 |
|
Pre-Award meeting
|
6 |
|
12/15/08 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
M.A. Mortenson Company |
Estimated Budget: |
|
$330,000 |
Awarded Cost: |
|
$271,212 |
Awarded Schedule: |
|
54 days |
Scope of Work: |
|
Removing & Replacing the suspended ceiling system & lighting |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|