University of Minnesota

University of Minnesota
Masonic Center

Project Overview
This project consists of replacing the existing fire alarm at Masonic Cancer Center, located at 424 Harvard St SE, Minneapolis campus in accordance with drawings and specifications.
Schedule

No
 
End Date
 
Task
1
 
11/28/06
 
Educational Meeting & Site Walk
2
 
12/14/06
 
Submittals Due
3
 
12/19/06
 
UMN Identifies Best Value
4
 
12/20/06
 
Pre-Award Kickoff Meeting
5
 
12/27/06
 
Pre-Award Meeting
6
 
12/29/06
 
Anticipated Date of Award

Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  Gephart Electric
Estimated Budget:
  $220,000
Awarded Cost:
  $205,085
Awarded Schedule:
  147 days
Scope of Work:
  Replace Fire Alarm System

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):
  9.9



If you have any questions please email John Savicky at John.Savicky@asu.edu
Contact Us