"M" Bridge Repairs

Project Overview
Contractor is to provide structural steel, painting and decking repairs as identified to the cable suspension pedestrian bridge identified in the documents as the “M” bridge.

Schedule

No
 
End Date
 
Task
1
 
7/29/08
 
Educational Meeting & Site Walk
2
 
8/7/08
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
8/12/08
 
UMN Identifies Potential Best Value
4
 
8/13/08
 
Pre Award Kick Off Meeting
5
 
8/20/08
 
Pre-Award meeting
6
 
8/20/08
 
Anticipated Date of Award

Award Information
Vendor Name:
  Cy-Con, Inc.
Estimated Budget:
  $50,000
Awarded Cost:
  $106,000
Awarded Schedule:
  38 days
Scope of Work:
  To provide structural steel, painting and decking repairs.

For detailed award information, click here (pptico XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here (pptico DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   10