UNIVERSITY OF MINNESOTA
"M" Bridge Repairs |
|
Project Overview |
Contractor is to provide structural steel, painting and decking repairs as identified to the cable suspension pedestrian bridge identified in the documents as the “M” bridge.
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
7/29/08 |
|
Educational Meeting & Site Walk
|
2 |
|
8/7/08 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
8/12/08 |
|
UMN Identifies Potential Best Value
|
4 |
|
8/13/08 |
|
Pre Award Kick Off Meeting
|
5 |
|
8/20/08 |
|
Pre-Award meeting
|
6 |
|
8/20/08 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Cy-Con, Inc. |
Estimated Budget: |
|
$50,000 |
Awarded Cost: |
|
$106,000 |
Awarded Schedule: |
|
38 days |
Scope of Work: |
|
To provide structural steel, painting and decking repairs. |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|