University of Minnesota
Lions Research Chiller Replacement |
|
Project Overview |
Consists of installing of metallic steam piping from TRF penthouse to Lions penthouse and removal and consolidation of existing chillers at Lions
|
|
Schedule |
No |
|
End Date |
|
Task |
1 |
|
9/22/06 |
|
Educational Meeting & Site Walk |
2
|
|
9/29/06 |
|
Submittals Due (Proposal, RA Plan, EEO) |
3 |
|
10/03/06 |
|
UMN Identifies Best Value
|
4 |
|
10/03/06 |
|
Pre Award Kick Off Meeting
|
5 |
|
10/09/06 |
|
Pre Award Meeting
|
6 |
|
10/10/06 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name : |
|
Egan Co. |
Estimated Budget: |
|
$143,000 |
Awarded Cost: |
|
$170,608 |
Awarded Schedule: |
|
65 days |
Scope of Work: |
|
Replace Chiller |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
9 |
| Final rating of contractor (10 max): |
|
9.13 |
|
|