Lind Hall Room 305 Remodel |
|
Project Overview |
Lind Hall room 305 is currently a classroom which, under this project, will be remodeled into a seminar room. Work consist of : repair and paint walls; fixed seminar table tops will be replaced; replace ACT; replace lighting; add power to seminar tables; new air conditioning unit and ductwork; replace perimeter radiation.
Work by the University: provide and install A/V equipment; HVAC controls;
This project will take place at Lind Hall Room 305, located at 207 Church Street SE, East Bank Campus.
|
Schedule |
| 1 |
|
4/06/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
4/15/2009 |
|
Submittals Due |
| 3 |
|
4/20/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
4/23/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
5/05/2009 |
|
Pre-Award meeting |
| 6 |
|
5/11/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Sheehy Construction |
Estimated Budget: |
|
$175,000 |
Awarded Cost: |
|
$142,665 |
Awarded Duration: |
|
32 days |
Scope of Work: |
|
Remodel classroom into a seminar room |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|