University of Minnesota
Kaufert Lab Window Replacement |
|
Project Overview |
The St. Paul District Facilities Management office has identified the need to replace exterior windows at the Kaufert Laboratory which consists of 2 buildings: East Building (Classrooms) and west building (Shop). This building is occupied by faculty and graduate students along with lab research areas. The majority of the windows on the East Building are single-pane wood framed fixed-casement with severely deteriorated frames, sills, sashes and non functional window hardware. The majority of the windows on the West Building(Shop) are single-pane, wood framed fixed-hopper windows, covered by a wood screen wall anchored back to the mullions. Similar to the East Building, numerous windows, sashes, sills and hardware are severely deteriorated. Other window types such as horizontal sliding and double hung windows may also be found. The existing window frames are rotting and glass panes fall out when the window is opened. Many of the windows have been modified by building occupants to fit their own A/C unit. Due to the lack of energy efficiency, inconsistency of window types and safety concerns the St. Paul District office would like to evaluate replacement options and design an energy efficient window plan for the entire building per current University Standards.
|
Schedule |
| 1 |
|
10/06/09 |
|
Educational Meeting & Site Walk |
| 2 |
|
10/20/09 |
|
Submittals Due (Proposal, RA Plan, EEO) |
| 3 |
|
10/28/09 |
|
UMN Identifies Potential Best Value |
| 4 |
|
11/03/09 |
|
Pre Award Kick Off Meeting |
| 5 |
|
11/17/09 |
|
Pre Award Meeting |
| 6 |
|
11/23/09 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
ATS&R |
Estimated Budget: |
|
$300,000 |
Awarded Cost: |
|
$32,750 |
Awarded Duration: |
|
108 days |
Scope of Work: |
|
Provide consulting services & professional analysis |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
|
|
 |