University of Minnesota
Johnston Hall Chilled Water & Sprinkler Install |
|
Project Overview |
It consists of installing the chilled water line and sprinkler system for Johnston Hall 1st Floor as per drawings which will be distributed at the site meeting at building, located at 101 Pleasant Street SE, Minneapolis campus in accordance with the drawings and specifications. Meet at the first floor entrance (on the Northrop Mall).
|
|
Award Information |
Vendor Name: |
|
MMC |
Estimated Budget: |
|
$119,000 |
Awarded Cost: |
|
$271,340 |
Awarded Schedule: |
|
57 days |
Scope of Work: |
|
Installation of chilled water lines |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
9.5 |
Final rating of contractor (10 max): |
|
9.5 |
|
|