Shepard Hall - Hydrogen Generator

Project Overview
This project consists of remodeling of hydrogen generator room.
Schedule

No
 
End Date
 
Task
1
 
8/02/07
 
Educational Meeting & Site Walk
2
 
8/15/07
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
8/16/07
 
UMN Identifies Best Value
4
 
8/17/07
 
Pre Award Kick Off Meeting
5
 
8/23/07
 
Pre Award Meeting
6
 
8/24/07
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or email the PBSRG contact listed below.
Award Information
Vendor Name:
  PMI Construction
Estimated Budget:
  $49,000
Awarded Cost:
  $49,755
Awarded Schedule:
  38 days
Scope of Work:
  Remodeling of hydrogen generator room
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  9
Final rating of contractor (10 max):   9.6