HH Humphrey Center Classrooms 15, 25 and 35 are operated by the Office of Classroom Management. This project will provide a much needed face lift to these three classrooms. Rooms 15 and 35 currently have recessed tiers, which under this project will be filled to provide a flush floor surface throughout. The tiered floor system in classroom 25 will remain and the seminar tables refinished. The scope of work, in general, to all three rooms will be: demo fixed seminar tables; patch and paint walls; replace chalk boards with white boards; replace carpet; new acoustic wall panels; new ACT; install card readers and automatic openers on existing doors; replace lighting; install / revise electircal power; install / revise raceways for A/V systems;
Work by the University: provide and install A/V equipment; HVAC controls;
This project will take place at HH Humphrey Center, located at 301 - 19th Avenue South, West Bank Campus.
|
Schedule |
| 1 |
|
4/13/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
4/23/2009 |
|
Submittals Due |
| 3 |
|
4/28/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
4/30/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
5/14/2009 |
|
Pre-Award meeting |
| 6 |
|
5/18/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
McGough Construction |
Estimated Budget: |
|
$190,000 |
Awarded Cost: |
|
$183,139 |
Awarded Duration: |
|
62 days |
Scope of Work: |
|
Demo fixed seminar tables, patch and paint walls, replace boards |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|