University of Minnesota
Residential Hall Door Replacement |
|
Project Overview |
Replacement of residential doors and locks at three dormitory buildings:
-Comstock Hall, 210 Delaware St SE
-Frontier Hall, 701 Fulton St. SE
-Centennial Hall, 614 Delaware St. SE
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
5/1/07 |
|
Educational Meeting & Site Walk |
2 |
|
5/16/07 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
5/24/07 |
|
UMN Identifies Best Value
|
4 |
|
6/06/07 |
|
Pre Award Kick Off Meeting
|
5 |
|
6/13/07 |
|
Pre Award Meeting
|
6 |
|
6/15/07 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
Tarraf Construction |
Estimated Budget: |
|
$300,000 |
Awarded Cost: |
|
$433,000 |
Awarded Schedule: |
|
43 days |
Scope of Work: |
|
Replacement of residential doors and locks |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
9.75 |
|
|