| Schedule |
No |
|
End Date |
|
Task |
1 |
|
7/25/07 |
|
Educational Meeting & Site Walk
|
2 |
|
8/07/07 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
8/08/07 |
|
UMN Identifies Best Value
|
4 |
|
8/09/07 |
|
Pre Award Kick Off Meeting |
5 |
|
8/15/07 |
|
Pre Award Meeting
|
6 |
|
8/16/07 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Tarraf Construction |
Estimated Budget: |
|
$33,000 |
Awarded Cost: |
|
$39,012 |
Awarded Schedule: |
|
23 days |
Scope of Work: |
|
Remodeling Real Estate Offices |
|
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
Final rating of contractor (10 max): |
|