Diehl Hall – Electrical Install

Project Overview
To install electrical outlets to various work station locations.
Schedule

No
 
End Date
 
Task
1
 
5/19/2008
 
Submittals Due (Proposal, RA Plan, EEO)
2
 
5/21/2008
 
UMN Identifies Potential Best Value
3
 
5/27/2008
 
Pre Award Kick Off Meeting
4
 
6/10/2008
 
Pre Award Meeting
5
 
6/12/2008
 
Anticipated Date of Award

Award Information
Vendor Name:
  Elliott Contracting
Estimated Budget:
  $30,000
Awarded Cost:
  $14,150
Awarded Schedule:
  12
Scope of Work:
  Install Electrical Outlets to various work station locations
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.77