University of Minnesota
Cooke Hall |
|
Project Overview |
Abandon the existing water service to Cooke Hall and install a new water service. The new water service shall split the domestic water service from the fire protection service once inside the building.
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
10/25/06 |
|
Educational Meeting & Site Walk |
2 |
|
10/31/06 |
|
Submittals Due (Proposal, RA Plan, EEO) |
3 |
|
11/03/06 |
|
UMN Identifies Best Value |
4 |
|
11/03/06 |
|
Pre Award Kick Off Meeting |
5 |
|
11/07/06 |
|
Pre Award Meeting |
6 |
|
11/09/06 |
|
Anticipated Date of Award |
|
| Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
MMC |
Estimated Budget: |
|
$50,000 |
Awarded Cost: |
|
$66,000 |
Awarded Schedule: |
|
148 days |
Scope of Work: |
|
Split domestic water service from fire protection service once inside of building |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
9 |
| Final rating of contractor (10 max): |
|
9.63 |
|
|