University of Minnesota
Comstock Hall - Pneumatic & Electronic
Controls Upgrade |
|
Project Overview |
Lot sum price for the modification of HVAC equipment in Comstock Hall as recommended by Sebesta Blomberg Engineers.
|
| Schedule |
No |
|
End Date |
|
Task |
1 |
|
4/17/2008 |
|
Educational Meeting & Site Walk
|
2 |
|
4/25/2008 |
|
Submittals Due (Proposal, RA Plan, EEO)
|
3 |
|
4/28/2008 |
|
UMN Identifies Potential Best Value
|
4 |
|
4/29/2008 |
|
Pre Award Kick Off Meeting
|
5 |
|
5/09/2008 |
|
Pre Award Meeting |
6 |
|
5/13/2008 |
|
Anticipated Date of Award |
|
Bidding / Proposal Information |
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG. |
|
Award Information |
Vendor Name: |
|
NAC Mechanical & Electrical Services |
Estimated Budget: |
|
$43,000 |
Awarded Cost: |
|
$48,960 |
Awarded Schedule: |
|
25 days |
Scope of Work: |
|
Modification of HVAC Equipment in Comstock Hall |
|
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
10 |
|
|