Comstock Hall - Pneumatic & Electronic
Controls Upgrade

Project Overview
Lot sum price for the modification of HVAC equipment in Comstock Hall as recommended by Sebesta Blomberg Engineers.
Schedule

No
 
End Date
 
Task
1
 
4/17/2008
 
Educational Meeting & Site Walk
2
 
4/25/2008
 
Submittals Due (Proposal, RA Plan, EEO)
3
 
4/28/2008
 
UMN Identifies Potential Best Value
4
 
4/29/2008
 
Pre Award Kick Off Meeting
5
 
5/09/2008
 
Pre Award Meeting
6
 
5/13/2008
 
Anticipated Date of Award


Bidding / Proposal Information
All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.
Award Information
Vendor Name:
  NAC Mechanical & Electrical Services
Estimated Budget:
  $43,000
Awarded Cost:
  $48,960
Awarded Schedule:
  25 days
Scope of Work:
  Modification of HVAC Equipment in Comstock Hall
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   10