Project Overview |
Dig up and repair an existing elevator pit drain, and restore interior damage caused when drain was not functional.
|
Schedule |
| 1 |
|
6/29/2009 |
|
Educational Meeting & Site Walk |
| 2 |
|
7/10/2009 |
|
Submittals Due |
| 3 |
|
7/15/2009 |
|
UMN Identifies Potential Best Value |
| 4 |
|
7/21/2009 |
|
Pre Award Kick Off Meeting |
| 5 |
|
8/10/2009 |
|
Pre Award Meeting |
| 6 |
|
8/12/2009 |
|
Anticipated Date of Award |
|
|
Award Information |
Vendor Name: |
|
Cy-Con Construction |
Estimated Budget: |
|
$52,000 |
Awarded Cost: |
|
$72,934 |
Awarded Duration: |
|
39 days |
Scope of Work: |
|
Dig up & repair existing elevator pit drain |
For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)
For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password. |
|
Closeout Status |
Vendor met proposed schedule: |
|
Yes |
Vendor met proposed cost: |
|
Yes |
Vendor met purposed quality/customer satisfaction: |
|
Yes |
Final customer rating of PIPS (10 max): |
|
10 |
| Final rating of contractor (10 max): |
|
9.9 |
|
|