Civil Engineering – Elevator Pit Drainage

Project Overview
Dig up and repair an existing elevator pit drain, and restore interior damage caused when drain was not functional.

Schedule

No   End Date   Task
1   6/29/2009   Educational Meeting & Site Walk
2   7/10/2009   Submittals Due
3   7/15/2009   UMN Identifies Potential Best Value
4   7/21/2009   Pre Award Kick Off Meeting
5   8/10/2009   Pre Award Meeting
6   8/12/2009   Anticipated Date of Award

Award Information
Vendor Name:
  Cy-Con Construction
Estimated Budget:
  $52,000
Awarded Cost:
  $72,934
Awarded Duration:
  39 days
Scope of Work:
  Dig up & repair existing elevator pit drain

For detailed award information, click here ( XLS). (This excel spreadsheet provides a summary of all the data that was collected. It is available only to pre-approved vendors). Please contact the PBSRG for the username and password.)

For a complete list of all project risks, click here ( DOC). (This document contains a list of all the risks that were identified by the vendors on this project. No solutions are identified, just a list of risks). This file is available to only pre-approved vendors. Please contact the PBSRG for the username and password.
Closeout Status
Vendor met proposed schedule:
  Yes
Vendor met proposed cost:
  Yes
Vendor met purposed quality/customer satisfaction:
  Yes
Final customer rating of PIPS (10 max):
  10
Final rating of contractor (10 max):   9.9